Storm Surges
Find out about Storm Surges and how they build...

 

Thames Barrier
Thames Barrier Why the Thames Barrier is too small and the menace of Global Warming...
What will happen?
Areas at risk from flooding and the threat of fire ...  
The Long Term
What will the effects of a flood be and is the Government awake to the danger...  

 

Thames Barrier

-History
-Technical Specifications
-Why the Barrier is too small
-Global Warming

 

Thames Barrier

History

1953. The worst storm surge of the last century hit the East Coast on the 31st January/1st February, 1953. It breached flood defences, knocked out tide guages between the Wash and Southend and devastated Canvey Island in the Thames Estuary. On Canvey alone, 58 people died and 10,000 had to be evacuated. The flooding extended into Docklands but Central London was spared.

1953 was a wake-up call for the government. Immediately a committee was set up to examine the risk to the capital. Thirteen months on, the Waverley Committee issued its report recommending that a storm surge barrier be built across the Thames.

Delays. From that point, things moved more slowly. Committee succeeded committee. Six possible locations were investigated and a variety of designs. With potential expenditure so huge, it is probable ministers found it convenient to stall. Ten years passed and other constructions claimed available funds. The M1 motorway was built while the Barrier was on hold.

In 1965, the newly created Greater London Council took over responsibility for flooding in the London area. Public anxiety was intense by this time and in 1970 work resumed on the Barrier project. A site at Woolwich reach was selected and an innovative rotating gate design.

Cost-benefit. An early decision had to be reached concerning degree of protection. To what height should the Barrier and associated defences be built? The result was a compromise between the engineers and the economists.

Economists think in terms of cost benefit analysis. They balance estimated damage against the degree of probability of the damage occurring multiplied by the cost of preventing it. With the help of data from the 1962 flooding of part of Hamburg, the Barrier economists reached an estimated damage figure for the tidal flooding of London of £2 billion (1966 values, equivalent to £20 billion today).

The Barrier was officially opened in May 1984. At a completion cost of £440 million it had run 75% over budget, chiefly due to inflation through the 1970's. Added to this sum was the expense of five minor barriers in the lower Estuary and a further £300 million for the raising and strengthening of over 70 miles of banks and defences downstream.

back to Barrier> top>

Technical Specifications

The Thames Barrier consists of a line of reinforced concrete piers spanning the river at Woolwich Reach and supporting steel gates. The exposed pier ends are disguised in curved housings made of timber clad with stainless steel. Their foundations are sunk 17 metres into the chalk.

Gates. There are four main navigation openings of 61 metres with rising sector gates and a further two 31.5 metre openings also with rising sector gates, for the use of smaller craft. To allow for free flow of tide through the structure, four more 31.5 metre openings are provided fitted with simple falling radial gates. In normal conditions the rising sector gates lie flat in concrete sills on the river bed to allow for free passage of river traffic.

The rising sector gates are hollow stainless steel structures, the downriver face curved to reduce load on the operating mechanisms. The gates are moved by means of reversible hydraulic rams and can be held in four different positions:

 

Thames Barrier Gate Mechanism

Thames Barrier Gate Mechanism

 

Gates in operation

 

Gates in operation

 

The main Control Tower, generators and workshops are located on the south bank. As a safety precaution there is a back-up control room on the opposite side. Two connecting service subways run through the concrete sills from bank to bank under the river, providing access to all piers. In a final emergency, gates can be manually operated from the individual pier engine rooms.

Closure. A decision to close the Barrier is taken by the Duty Controller on the basis of data provided by the Met Office and the Barrier's own computer model for the Estuary. Closure is usually four or five hours in advance of high water. Before the Barrier is closed, the Port of London is notified so that shipping in the area can be warned. Navigation signals on the Barrier piers change to indicate closure and up and down river special signboards are illuminated.

The operating sequence is designed to cause minimum interference with the normal flow of the river. The four falling radial gates are closed first, then the main gates are raised starting from the outside and working in. Each gate is independently monitored and operated from the Control Room.

As at 29th April, 2002 the Thames Barrier has been closed 276 times. Sixty-four to protect London from tidal flooding, three to assist in preventing fluvial flooding, one for salvage work on the Marchioness and one for repair works following the Sand Kite incident. The other occasions were routine monthly closures for experiments and tests.

Click here for Thames Barrier -Facts and Figures


back to Barrier> top>

Why The Barrier Is Too Small

The ideal Barrier. With hindsight, the approach the Barrier designers should have taken is clear. They should have looked at the two components of a storm surge independently and built to withstand the unlikely, but many fear inevitable, future event. The combination of the highest surge residual recorded riding on the back of a high spring tide.

To make sense of this, take some of the figures for surge residuals. Using the storm of 1953 for comparison, we see the surge residual as a long drawn out hump, the highest peak occurring near the beginning and measuring 2.59 metres at Sheerness/Southend.

This is high for a surge but by no means the highest on record. At the same location, a surge in 1894 reached 2.9 metres; one in 1905, 3 metres; one in 1921 3.35 metres and one in 1943 a massive 3.66 metres.

Surge Residual Profiles at Sheerness/Southend 1905, 1921, 1943

Surge Residual Profiles at Sheerness/Southend 1905, 1921, 1943


Despite their great elevations, none of these surge residuals resulted in exceptionally raised sea levels because they all fell away well before high water.

But suppose they had not. What if the peak of the surge of 1943 had coincided with high water of a mean spring tide, 2.71 metres ODN or more frightening still one of the highest spring tides, 3.20 metres ODN?

This would give potential sea levels at Sheerness/Southend of 6.37 and 6.86 metres ODN. Both hugely in excess of the 4.69 metres ODN that caused massive damage in 1953.

The actual Barrier. It may be that the ideal approach was just too alarming or too expensive to consider. Barrier plans had been shelved often enough before and the GLC was determined that this time some form of protection would be built.

Instead of looking to the worst combination of surge residual and astronomical tide that might happen, the design team went back to storms that had actually happened in the past.

Using historical tide guage records and a mathematical relationship to obtain frequency distributions, they extrapolated probabilities of specified heights occurring in the future. Based on these probabilities, they set a height for the Barrier of 6.9 metres with adjacent riverbank defences at 7.2 metres.

At this level, according to the calculations, the Barrier could be expected to contain the 1000-year event at least until the year 2030. The 1000-year event in the design projections being a reading of just over 5.5 metres ODN at Sheerness/Southend.

The calculations. In addition to the question mark over approach, there are concerns over certain features of the Barrier design calculations. Three areas in particular merit a closer look.

1. Tidal records. Statistics are only as good as the data they are based on and historical tide gauge records are gappy and inconsistent. For the mouth of the Estuary, crucial to the frequency distribution on which Barrier design was based, only 104 'reasonably complete years' were available between 1819 and 1953.

2. Date limit of 2030. This relates to an adjustment for the projected rise in high water in central London. This rise has nothing to do with surges. It is caused by a variety of factors including change in global-mean sea level, geological settlement of southern England due to tectonic movement, and effects of human disturbance such as dredging and embanking. Until recently the rise has been a steady 0.8 metres per century. As a measure of economy, Barrier designers added only 0.4 metres to their calculations to cover the rise expected over fifty years or until the year 2030. The joker in the pack here is global warming.

3. Allowance for amplification of the surge as it passes upriver. This funnelling or 'squeeze' effect is caused by the trumpet shape of the Estuary. It has increased with the straightening and raising of the river banks and scouring of the bed by currents. Barrier designers considered they were being generous in allowing 1.5 metres. A check of tide tables questions this. While the difference between high tide levels at Sheerness/Southend and London Bridge is normally around a metre, 1.2 metres is not uncommon for higher spring tides. Add the 0.3 metre allowance for wind and wave freeboard and 1.5 metres is already reached. And that is without the extra input from a surge.

Taking the argument one step further, suppose the allowance is viewed as a percentage rather than as a finite amount. This is an equally valid approach and one which a number of scientists favour. Rough calculations suggest an amplification of between 35 and 50%.

Add 35% to the figure to the 5.5 metres ODN figure for Sheerness/Southend on which Barrier design was based and the result is 7.43 metres. Well over the top of both the Barrier and surrounding defences.

back to Barrier> top>

Global Warming

More unpredictable and extreme systems, more frequent and violent storms, more widespread flooding and drought. Environmentalists have been crying in the wilderness for years. Now the world's big insurers are also panicking about climate change. Premiums against hurricanes and floods are set to rocket. Industry statistics show that, compared to the 1960's, the number of really big weather disasters has increased fourfold.

The culprit is generally accepted to be global warming, but evidence is hard to pin down. There is, however, one specific effect which is readily measurable.

Global mean-sea level. Historically, global mean-sea level has risen by around 0.22 metres per century. The melting of glaciers and polar ice threatens to accelerate this rise. Recent forecasts suggest a 0.31 metre increase. Many environmentalists fear more.

In the Barrier design, a global-mean sea level rise of 0.22 metres was incorporated in the figure of 0.4 metres for increase in high water in central London over fifty years. If the rise turns out to be more than 0.22 metres, Barrier calculations appear vulnerable.

Taking the 'most likely' projection, a 0.31 metre rise in global level, the Barrier design allowance will be exceeded round about the year 2030. This is the time when the designers themselves thought improvements might have to be made. With the less optimistic forecast the allowance could be surpassed as early as 2010.

This does not mean that flooding is certain, but it does alter the probabilities in the design calculation. With the 'most likely' projection, the 1000-year event becomes a 500-year event by the year 2050. In other words a doubling of the probability of occurrence of an over-Barrier flood in any particular year. Using the 'worst' projection, the same state is reached by 2015.

And one last point: by the year 2070 for 'most likely' and by 2040 for 'worst' case, the 1000-year event becomes a 100-year event. This is close to the original probability of occurrence of the 1953 flood, deemed an unacceptable level of risk and justifying construction of the Thames Barrier.

back to Barrier> top>

Print Print this page

 

 

©2002 Richard Doyle. All rights reserved